$4.8M To 7 Companies For 3 Years Mountain Snow Plowing

Acting as the governing body for county’s various county service areas and their zones, the board of supervisors last week approved contracts totaling $4.8 million with eight companies to perform snow removal services on mountain roads within those service areas and zones and on adjacent county-maintained roads from November 3, 2015 to June 30, 2018.
Under that agreement, Lake Arrowhead Construction, Inc., doing business as Trinity Construction of Blue Jay, is to receive no more than $175,000 annually, for an aggregate amount of $525,000 over the term of the contract.
Bacon/Wagner Excavating, Inc. of Running Springs, will be paid no more than $100,000 annually, for an aggregate amount of $300,000 over the term of the contract.
William Kanayan Construction of Rim Forest is to receive no more than $175,000 annually, for an aggregate amount of $525,000 over the term of the contract.
Porter’s Firewood of Big Bear City, is to receive up to $500,000 each year, for an aggregate amount of $1,500,000 over the term of the contract.
Ken Willis Construction, Inc. of Big Bear City, is slated to do work in return for annual remuneration not to exceed $275,000, for an aggregate amount of $825,000 over the term of the contract.
Bear Valley Paving of Big Bear Lake, is to be paid no more than $100,000 on a yearly basis, for an aggregate amount of $300,000 over the term of the contract.
GM Excavating, Inc. of Running Springs, was qualified to do work capped at a yearly limit of $175,000, for an aggregate amount of $525,000 over the term of the contract.
Altmeyer Inc. of Cedar Glen, is to be paid no more than $100,000 annually, for an aggregate amount of $300,000 over the term of the contract.
Each of the contracts carries with it a two-year option to extend.